City of Phoenix
Transit Chiller and Pump Replacements
Scope of Work:
- Removed a 400 ton chiller and two chilled water pumps
- Installed (3) 125 ton chillers and (2) chilled water pumps
- The (3) chillers were piped together with space available to add one more
- Upgrades were made to electrical and controls to accommodate the new units
- Chilled and condenser piping were reconnected to existing building systems
- Added a new exhaust system and refrigerant monitoring system
- New chiller was factory started and programmed
- System was independently tested and balanced